Timetable

The council has announced the following timetable for consultation.

Valid 

31 August 2006

1488 consultation letters sent

14 September 2006

Invitation letters for planning forum sent

5 October 2006

Planning Forum now in Council Chamber not Market House. Letters to go out. 

24 October 2006 (in Council chamber)

Kingston Town Sub Committee for comment

22 November 2006

Development Control Committee

13 December 2006

16 week expiry date (EIA Applications)

21 December 2006

GLA 14 days   

05 January 2006

The application can be seen on the council site at
http://maps.kingston.gov.uk/planning/Planning_DETAIL.aspx?strCASENO=0612424